If you are looking to implement a microsite yourself, please see these instructions.
Please review this table regarding how each step of the process is handled.
|
Task |
Typically |
Average time it takes |
|
|
Owned by |
Supported by |
||
|
Wireframe development |
Agency with guidance by Global Product Team and Local Affiliate |
Global Support Team provide feedback (optional) |
1-4 weeks, depending on complexity and local reviewers |
|
HTML/CSS development and testing |
Agency |
Global Support Team provide feedback (optional) |
2-8 weeks, depending on complexity. |
|
Localization |
Local Affiliate |
Agency |
0-4 weeks, depending on number of languages, site content, and how the microsite is developed. |
|
Implementation of microsite into WCMS |
Global Support Team |
Global Product Team or Agency to answer any questions if there are issues with integration |
1-5 days per microsite, depending on complexity, when whether Global has been involved in earlier steps. Will be shorter if Global is familiar with the microsite. |
|
Final User Acceptance |
Local Affiliate and Global Product Team |
Global Support Team |
1-3 days. |
|
Go-live |
Global Support Team |
Local Affiliate and Global Product Team informed |
1 day. |